Little Cheyne Court Wind Farm
| Little Cheyne Court Wind Farm | |
|---|---|
Little Cheyne Court wind farm, close to power lines running to Dungeness Nuclear Power Station | |
| Country | England, United Kingdom |
| Location | Romney Marsh |
| Coordinates | 50°57′45″N 00°49′13″E / 50.96250°N 0.82028°E |
| Status | Operational |
| Commission date | April 2009 |
| Power generation | |
| Units operational | 26 x 2.3 MW |
| Make and model | Nordex: N90 |
| Nameplate capacity | 59.8 MW |
| External links | |
| Commons | Related media on Commons |
The Little Cheyne Court Wind Farm is located 7 kilometres (4.3 miles) west of Lydd on Romney Marsh. It was built by npower renewables and cost around £50 million. The 26 wind turbines, each 115 metres (377 ft) high, are distributed over an area of 4 km2 (1.5 sq mi) with peak generation of 59.8 MW.